RE:RE:BTWBaitingBateman wrote: TGIF is retrofitting the 12k sf building for production. The 67k sf building is constructed from the ground up - footings and all. The only thing previously existing in the site were fittings and piers, of which nothing was repurposed. Unlike you Blaine, I actually have kept copies of the floor plans and know how to look into permit documentation from CC. Shall I give you another lesson?
Blainelinton wrote: Medmen's 45k facility was a 15mm 2 year project built from the ground up, there's a huge advantage and savings having TGIF only retro fit an existing building. There's no f@cking way you can even begin to compare the two.
Nope footings poured.
https://www.proactiveinvestors.co.uk/companies/news/187252/friday-night-moves-closer-to-construction-at-its-new-growing-facility-187252.html
Sounds like fittings and hydro connections in place as well.