fantatic update The construction project remains on budget and on schedule for start of production in November 2018.
The overall project, including procurement and construction activity, is 77% complete with just under 14,000 manhours worked to date. No lost time safety or environmental incidents have been recorded.
Mark McCauley, Melior CEO, said, “The site is looking fantastic and the project remains on track for start of production in November. An experienced operations team is starting to assemble on site with detailed planning of the soon to be commenced commissioning process being the focus for the team.”