Next Update?We should be receiving an update in the next few days. I am anticipating a release by week's end as commissioning should be close to finalizing and production about to begin that is assuming no huge problems were encountered during the breakin period. Our process is fairly straight forward so barring a major glitch, we should soon be good to go.
As I recall around 30,000 tons are need for the shipload and the mill will produce about 1000 tons per day when operating so we should expect our first shipment in early January. It will not likely be before this date because of startup and Xmas.
The first six months of 2019 should be interisting times for HUD shareholders with a lot of activity to come with new agreements and,hopefully,positive cashflow. If this materializes ,we can expect an increased SP prior to any financing to meet the upgrades needed for new off-takes.