RE:Merry Underground X-mass & Happy Almonty 2019Does that mean they encountered a 100M strike length of tungsten ore or that they have completed 100M of transportation drifts?
According to the November 27th NR, they will complete 4,000M of drifts,bays and croscuts in 18 months which is 220M per month. The NR states they began work 3 months ago on September 26th.