RE:What happened to the other 9 rooms?@ Transporter : Jan. 2, 2019
- As of calendar year-end, 7ACRES has 19 completed flowering rooms
- Completion of all 25 flowering rooms scheduled for March 2019
- Administrative offices and other facilities scheduled for completion by mid-2019
- Health Canada approval of additional flowering rooms expected in the near term
An updated timeline of construction completion is as follows:
- December 2018 – 19 total flowering rooms completed.
- January 2019 – 3 additional flowering rooms are expected to be completed.
- February 2019 – 1 additional flowering room is expected to be completed.
- March 2019 – 2 additional flowering rooms are expected to be completed, representing the completion of all 25 flowering rooms.
- Mid-2019 – primary office and administrative area are expected to be completed.