Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Euro Sun Mining Inc T.ESM

Alternate Symbol(s):  CPNFF

Euro Sun Mining Inc. is a Canada-based mining company. The Company is focused on the exploration and development of its 100%-owned Rovina Valley gold and copper project located in west-central Romania. The Company holds the Rovina Valley Project through a mining license which covers a total of 27.68 square kilometers (km2). The Rovina Valley Project consists of three copper-gold porphyry systems referred to as Rovina, Colnic and Ciresata. The Colnic Deposit is located approximately 2.5 km south of the Rovina Deposit and the Ciresata Deposit is approximately 4 km south of the Colnic Deposit. The Rovina gold deposit holds about 400 million tons of confirmed resources containing 7.0 million ounces of gold and 1.4 billion pounds of copper.


TSX:ESM - Post by User

Bullboard Posts
Comment by urai58on Apr 11, 2019 8:39am
147 Views
Post# 29611487

RE:It’s not too late

RE:It’s not too late
SamCosbyJr wrote: Still time to watch ESM. Check this out 

https://bit.ly/2KHm03x


There is nothing guaranteed fast. That's the way to production.
  1. General Urbanization Plan (“PUG”): land use approval for new categories on a local and regional area basis (includes public meetings for feedback and approval).
     
  2. Zonal Urbanization Plan (“PUZ”): land use approval for industrial zones including detailed development plans (includes public meetings for feedback and approval).
     
  3. Environmental procedure requirements through local environmental protection agency
     
  4. Approval by the local County Council.
     
  5. Environmental License.
     
  6. Environmental and Social Impact Assessment approval (“ESIA”)
     
  7. Closure and Remediation plan
     
  8. Technical Authorization Committee (“TAC”) approval. The TAC is comprised of experts and interested parties from recognized institutions.
     
  9. Public hearings for feedback.
     
  10. TAC and company review of public feedback (as per the Equator Principles).
     
  11. Approval from the Regional Environmental Agency.
     
  12. Contruction Permit issuance, allows construction to begin.
     
  13. Operational License.
 
At least 2 years plus 1 romanian year (post-communist bureaucracy with apparatchiks.
 
 