Current Development Projects For TA and RNW.Big Level - 90 MW Pennsylvania project
15-year PPA with Microsoft
Capital cost of ~US$178 million
Commercial operation expected in Q4 2019
Funded in TransAlta Renewables
..........................
Antrim - 29 MW New Hampshire project
20-year PPAs with Partners HealthCare (75%) and New Hampshire Electric Cooperative (25%) Capital cost of ~US$81 million
Commercial operation expected in Q3 2019
Funded in TransAlta Renewables
..........................
Windrise - 207 MW Alberta REP project
20-year contract with the AESO
Capital cost of ~$270 million
Commercial operation expected in Q2 2021
Potential drop-down asset to TransAlta Renewables
..........................
Skookumchuck – Net 67 MW Washington project
49% interest in the project
20-year PPA with an investment grade counterparty
Capital cost of ~US$120 million
Commercial operation expected in late December 2019 or Q1 2020
Potential drop-down asset to TransAlta Renewables
With all the current development projects mentioned above,
why would you sell!!!
To read more go to: https://www.transalta.com/wp-content/uploads/2019/08/Q2-2019-Results-Presentation.pdf