CC QuestionDid anyone else hear them say that they had 1 month of stored products?
April production was reported to be 480mt.
Here's what they reported.
The Company's planned upgrades to the kiln and improvements in the cooler have been postponed until further notice as a result of precautionary measures such as limiting mine site personnel and contractors in light of the COVID-19 pandemic. This work is not expected to have an impact on the Company’s production.
The Company instead performed an enhanced preventative maintenance program in the chemical plant for approximately 15 days and, as a result, April 2020 production was 480 tonnes of V2O5.
I am wondering if Glencore will make a claim for the stored product to make up their April production shortage.
Just wondering.