Comment by
Scanner454on Aug 03, 2020 9:28pm
243 Views
Post# 31359153
RE:construction
RE:constructionfrom what i know and have seen on schedule.....new ball mill in,roof still open but cross members of roof in place....currently working on getting ball mill configured to run...electrical in place and software/hardeware being put through their paces....one enviromental concern still being worked out...operational wise have hired key mgt. personel as well as operational staff....have some current ariel pictures of the site but have to figure out how to post them...impressive in my view