My understanding is that it would take a year to pump all the wather from the open pit and purify to remove the zinc residues.
If we were confident that the financing could be obtained within a year either from revenue from Elder and SG and or add dept we should start immediately.
I do not know what the $35-40M needed to restart will be spent on.
Is it a few $m to pump.
$15m to put the mill in operation.
$15m to buy trucks and extra equipment .
Maybe the poster that has worked with mill could help clarify this.
Maybe we should start the mill now and look into processing mineral from Vendome if it could be done faster.
I know all suggestions from a man that has no understanding how mining works, but a discussion has to start somewhere.
Fernand