RE:webinarA few other things of note:
1) Currently paying a 10% market premium for ewaste, presumbably because the process needs third-party validation. Expecting to pay no premium in about a year.
2) Ewaste production expected to increase to 200 tonnes per month in March 2021 and to 300 tonnes per month in July 2021.
3) First ewaste royalty plant projected to begin operations in October 2022.
4) For the conventional mining sector, forecasting mine plant engineering being complete in January 2021, with the first royalty plant operating in July 2021 and the second plant operating in October 2021.