Nyngan scandium projet developpement?
Hi folks, I'm in SCY since near 3 years now and it make long time (2017-2018) that no more developpement news come for this projet. Is there somebody know something about it since 2 years? Is it on hold or it's remains in progrs. Here a screen shot from the Web site : "The Project schedule identifies 2017 as the initial year in the cash flow, with construction initiated and completed in that year. Some commissioning is scheduled for Q4 2017. Further wet commissioning and start-up is scheduled for Q1 2018. First production is planned for March 2018, which is year 1 of 20 (calendar) years of production, completing in 2037. Reclamation of the Residue Storage Facility is scheduled for 2038. The supply and delivery estimate on the specialist autoclave and flash vessels is setting the timeframe for first production in Q1 2018." Good news this Rio annoncement! Could be a great timing for everyone here!