RE:Timeline As new info has appeared the timeline needs some corrections.
Ca. 17. March - first testresult from Cascadura d (or at least that week
25. March - flowtest from oilbearing zone at Chinook (downhole pump will be installed early next week followed by probably one week test)
24. March - 30.April - testresults from Cascadura d and Chinook as they go
Mid April - Coho online - 500 000 $ pr month
Late April/early May - spud Royston
June - Royston TD
June/July - testresults Royston
And through the autumn we will face Steelhead(contingent on the cost and outcome of the Royston well) and some oilwells at Legacy property and of course Chin and cas online
Deep prospect at Legacy in Q4