Dramatic AISC reduction (Part2)«
- Low unit costs, including average operating cash costs of $524 per ounce and all-in sustaining costs per ounce of $775 in first five years (2021 to 2025);
Projecting the Q1 2021 production and using AISC of $ 775 /oz
................Production.....AISC...total
Detour 170 000 $ 775 131 750 000
Macassa 52 000......$695 36 140 000
Fosterville 150 000.....$ 314 47 100 000
Total 372 000 .................$.214 990 000
.........AISC $ 578 /oz....
AISC considering $ 775 in first five year (2021) as per report
As a complement information :
Results AISC for 2020 $ 800/oz
Guidance for 2021............AISC $ 790/$ 810 /oz
So it seems lokely that we may expect a dramatic drop in the AISC in the coming quarter and up to $ 222 /oz
Quite clear that KL will become a ''stunning'' AISC gold producer in the next futur.
Great numbers.