RE:RE:RE:What doe this sentence mean? Hi RockDoc1,
The plan went awry in Januaryas the status pointed to the normal comissioning issues yeilding 1054 tonnes per day with a target of 5KTpd for "mid 2021". An incrase of 60% over November.
In Feburary the target was 3000Tpd actual was 1600 Tpd. "due to mechanical issues"
In March we got a "Tpd missing" status - this bothered me - I would prefer a Tpd average even if it is approaches zero.
Our latest status most concerning issue was the extra effort on the water bearing dike. Is this a "simple" lining issue or are we talking about sustaining pumps over the long haul? I understand pumps are standard as stated in the tech report.
The batching comment was expected. The stopes are 100ftx50ft and 75ftx50ft. as per the tech report. - the volume progress is easy to calc and turn into TPD.
I was a bit surprised on the ventalation issue as they are not blasting stopes yet - and the gear is mostly if not all electric (BEVs).
So my interpretation of the latest status was that until they get the new fans in place they will be linited on the Tpd production. With the ug fans and without the surface fans what do we expect to see for tps ? 3000? and then that level until the surface fans are running?
Tks for being patient - still learning - Cheers ttc