Murchison Will Be The Cornerstone of Monument..100,000 ounceHow stunned of me.
I had to go back to Kentor's 2012 four phase plans for a fully developed Murchison production plans which included heap leaching the low grade oxides, fully developing Gabanintha and its copper resources and doubling the Burnakura mill to 500,000 tons per year .
Projected production was 70,000 ounces of Gold and 16 million lbs of copper per year .
Note that Monument wants to increase mill capacity to 750,000 tons per year which would boost gold production to 100,000 ounces per year .
Plus, we have Selinsing soon to be capable of at least 50,000 ounces per year, excluding the sulphide resources which must await Biox.