Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Novo Resources Corp T.NVO

Alternate Symbol(s):  NSRPF

Novo Resources Corp. is a gold explorer focused on discovering gold projects. The Company is engaged primarily in the business of evaluating, acquiring, exploring, and developing natural resource properties with a focus on gold. It has a land package covering approximately 5,500 square kilometers in the Pilbara region of Western Australia, along with the 22 square kilometer Belltopper project in the Bendigo Tectonic Zone of Victoria, Australia. Its key project area is the Egina Gold Camp, where De Grey Mining is farming-in to form a JV at the Becher Project and surrounding tenements through exploration. The Company is also advancing gold exploration at Nunyerry North. It focuses on undertaking early-stage exploration across its Pilbara tenement portfolio. It has also formed a lithium joint venture with SQM Australia Pty Ltd (SQM) in the Pilbara, which provides shareholder exposure to battery metals. Its Belltopper Gold Project comprises the adjacent Malmsbury and Queens projects.


TSX:NVO - Post by User

Comment by HuberPeteron May 16, 2021 11:44am
117 Views
Post# 33211322

RE:RE:RE:RE:RE:Head grade first months of production

RE:RE:RE:RE:RE:Head grade first months of production

Cash costs (costs of good sold) couldn't be calculated because of capitalization of all costs to ramping up cost til beginning of commercial production.


HuberPeter wrote:

Hi tx,

if you make some DD of the published recent md&a and financial report you will assume that I should be right.

Processing tonnage of april is reported; oz sold are reported; they should have sold like in q1 about 80% of production (5 days backlog production)

oz in circuit and in stockpile til end of March are reported. 


This assumptions give me a picture that head grade was not above 1.1 g/t in between April and mid May.

wouldn't be sure that theese problems will not affect Egina; but at least Karratha. Grade Control is the Problem. Sure - there is another concept of mining at Egina. Netherless the fear of scaling up from mak to big bulk mining would be high. 

but doesn't really matter. Novo is current on the path of producing about 40.000-50.000 oz per year. Til infill results reporting there is no sight of significant improvements. 

infill drilling will show if it is a grade Control problem or a cause overestimation of the reported oz respectively the grade at maiden. 

Peter 

 

TXRogers wrote:

 

HuberPeter wrote:

What should he say? He is a promotion man. 


many promises couldn't be kept. No capital raising, no infill; just mining;

maybe without ni43-101 ...

this problems will have an impact for the business case of Karratha and Egina too. 

 

VilleValium wrote:

 

HuberPeter wrote:

headgrade mid Feb - mid
Using the md & a and financials from q1 and the md & a, I analyzed an approximation of the head grade by mid-April.


Q1 / 21
first pour oz mid Feb21
revenue: 7.6m cad valued at 1800 usd / oz = 3400 oz sold
stockpile: 800 oz + 150 oz in the circuit results in approx. 4200-4500 oz production for 1.5m including tailings
= approx. 2,900 oz per month in the ramp up Feb and March
April - Mid May oz sold: 8800 + 1000 oz stockpile incl circuit
= approx. 9800 oz prodction ergo: 5400 oz production for 1.5 month = 3.600 oz per month (90% utilization)

processing: 108,000 April (md & a) + 60,000 half of may = 168,000t
Head grade: 0.9 - 1.1 g / t
Recovery: 92%

I find it particularly problematic that the headgrade did not recover in April until mid-May. According Pea a head grade of 2.16 g / t is targeted. It will be interesting to see how the headgrade changes with the processing of the high-grade reef. However, according to the PEA, a head grade of approx. 2.1 g / t was also shown in the first year.

As feared, this is not a ramp-up problem and no significant improvement is to be expected in the next few months.

Peter

 


Really? So then why will Q be saying the opposite when he does his interviews this week. Normal startup issues. Mere mortals cant understand how complex this stuff is. 

VV



A couple of things, Peter.

Your comment "I find it particularly problematic that the headgrade did not recover in April until mid-May."   I wouldn't be so sure on that assumption.

And regarding Karratha and Egina:  Those projects will not undergo the same process or business case as Beatons Creek.  And neither will the resulting headgrades of the ore concentrate that makes it way across the Pilbara to the mill.

As for the latter Karratha / egina type projects, I would not be putting the cart in front of the horse just yet.

Tx




 




<< Previous
Bullboard Posts
Next >>