WDO - Today's Conf CallSurprise updates from todays Conf Call:
1) Spending at Kiena to expend to 79 Million. 38 million to date, +10 million on a paste plant. Expect 20 Million more in both Q3 & Q4
2) Mill restarted in July. Current production is 40 tonnes per hour = approx 1000 tpd
3) Running low grade S Zone material (4-5 gpt)
4) Foot wall corredore is 50 m wide and extends 300 m to date.
5) trending to high end of guidence... expect a revised guidence number in Q4
6) Expecting new drill results "shortly" for Kiena & Eagle