RE:RE:RE:Today’s meeting Lead time on components went through the roof since beginning of the year. If they have not yet contracted with a construction partner, it will take at least 4 weeks before they can even order any component (detailed engineering), after which it will take somwhere between 6-8 months for delivery of all components, around 6 weeks assembly, 2 weeks for SAT and commisioning.
That is if everything goes well, which rarely happens.
So realistically, no production is to be expected until Q4 2022.