RE:Joint Review Panel Invites Comments on Draft Public HearingThe last webinar, Kerry said Mgt was meeting with govt & 1st nations that day. Jamie last said they expect Agreements. Using the SB $500m invest into the lithium company, their permits are not expected until 4th qtr of 2022. Taking everything in on Marathon, it's always seemed to me getting the 1st Nation agreements, is short-term key. Even over the 2022 permits. Keep in mind, the confidence in mine design / permitting, is why they're going to be ordering items now. Look @ Noront as an example --- not ordering items until the typical post permitting. John McBride has been on Marathon for 13 yrs. It's paying off now. :)
Securing millions for the detailed engineering, etc. now, is also huge signal somebody agrees on that dual path approach.