RE:A reply from Gary at Aurcana...cartpathcarl wrote:
... The mill has operated at 325 tons per day (feasibility states 270 tons per day), so we feel like we are well on our way now.
We will ship out concentrate bags this next week, go into commercial production in November and be cash flow positive in December.
Thanks for your very helpful information. 35 tonnes per day is very good, but is this the level of production observed throughout the month of October, since, the first or was it still a start-up and test phase? Can we expect monthly production for October on the basis of 31 days at over 300 tonnes per day on average?