Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Ivanhoe Mines Ltd T.IVN

Alternate Symbol(s):  IVPAF

Ivanhoe Mines Ltd. is a Canada-based mining, development, and exploration company. The Company is focused on the mining, development and exploration of minerals and precious metals from its property interests located primarily in Africa. Its projects include The Kamoa-Kakula Copper Complex, The Kipushi Project, The Platreef Project., and The Western Foreland Exploration Project. The Kamoa-Kakula Copper Complex project stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, approximately 25 kilometers (km) west of the town of Kolwezi and about 270 km west of the provincial capital of Lubumbashi. The Kipushi mine is adjacent to the town of Kipushi in the Democratic Republic of the Congo (DRC) approximately 30 km southwest of the provincial capital of Lubumbashi. The 21 licenses in the Western Foreland cover a combined area of 1,808 square kilometers to the north, south and west of the Kamoa-Kakula Copper Complex.


TSX:IVN - Post by User

Post by guarantor1on Nov 01, 2021 9:19am
662 Views
Post# 34072276

BMO re IVN, Nov 1

BMO re IVN, Nov 1

November 1, 2021 | 08:52 ET | 08:52 ET~

page1image3305640832

Ivanhoe Mines

IVN-TSX Rating Price: Oct-29 Target Total Rtn Outperform $9.71 $15.00 54%

Kamoa-Kakula Phase 1 Reaches Steady State; Phase 2 60% Complete

Bottom Line:

Ivanhoe's monthly Kamoa-Kakula production update this morning announced 16,211 tonnes of copper produced as Phase 1 reaches steady-state design capacity, and narrowed guidance to 90-95,000t (the upper end of the previous 85-95,000t). Phase 2 construction continues with completion reaching 60% and evaluations for an expanded Phase 3 and construction of a smelter are both underway. We expect optimization of Phase 1, construction of Phase 2 and plans for Phase 3 to revalue Ivanhoe's shares.

Key Points

October's copper production was 16,211 tonnes (to October 20) and on October 25 delivered a new daily production record of 729t; Phase 1 targets production of 16,666t/month. The Phase 1 processing plant is now operating at design rates, with ore throughput exceeding design capacity by 2%; IVN notes that it expects ongoing optimizations at the plant to further increase its production. Ivanhoe added a second filter press earlier in the month that removes a bottleneck from the processing circuit, and copper recovery in October at 85.1% was close to design recovery of 86%.

2021 production guidance was narrowed to 90-95,000t as October production came in strong despite power supply issues, with intermittent blackouts at Kamoa-Kakula for the first three weeks of the month due to regional transmission issues (which IVN is working to help correct). Ivanhoe also maintained mining production despite facing significant water inflows in the northern part of the mine that have been resolved; mining rates continue to exceed milling rates and surface stockpiles have grown to 3.73Mt at 4.72% copper.

Construction of the Phase 2 concentrator plant is 60% complete after passing
the 50% mark in September. Construction is currently focused on structural steel and equipment installation, and electrical cable installation has started. Final deliveries of structural steel, piping and platework are expected by the end of November. Phase 2 is expected to start production in Q2 2022 and will double production capacity at Kamoa- Kakula.

Planning is underway for an expanded Phase 3. The scoping study for an expansion of Phase 3, which was originally intended to replicated Phases 1 & 2, is expected to be finished in 2022. Ivanhoe is also evaluating building a smelter near the mine to produce up to 500,000tpy of copper in blister and has initiated EPCM work to advance the concept.