Santana Mine Update Minera Alamos Announces Santana Mine Operations Update
Rapid Leach Kinetics Continue as Mined Gold Inventory Exceeds Year-End Targets
Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - December 7, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an update of the ongoing ramp-up of mining activities at the Santana gold mine in Sonora, Mexico. Through the end of November 2021 in excess of 7,300 ounces of gold have now been placed on the leach pad since the expansion of mining activities was initiated in August; the majority stacked during the 3 months of September, October and November. Mining operations continue to progress with approximately 100,000 tonnes of new mineralized material stacked on the leach pad in each of October and November.
Operational highlights through November 30th, 2021
-
Gold inventory on the leach pad (7,330 oz) has exceeded original year-end target levels
-
Cumulative gold recovery from mineralization under leach for more than 30 days is approaching 70% (additional recovery ongoing)
-
Total area of stacked mineralization under active leaching continues to expand and is currently in excess of 50%
-
Reagent consumptions remain low and in line with previous test pad results (<0.2 kg/t NaCN and <2 kg/t lime)
"The results from our early operations at the Santana project continue to impress," stated Darren Koningen, CEO. "Metallurgical extractions have been outstanding to date and despite challenges the build up in gold inventories on the leach pads has exceeded our early expectations. The Company looks forward to providing further updates as the ramp-up in operations approaches its final stages with a goal of achieving steady state performance in the first quarter of 2022."
Ongoing Gold Extraction and Project Ramp-up Performance
Gold extraction from mineralized material stacked on the Company's leach pad continues to demonstrate rapid leach kinetics similar to those reported previously and in-line with the results demonstrated during earlier test plant operations at site. The total ounces under active leaching operations (more than 30 days) have more than tripled since the Company's previous update (see news release dated November 4th 2021) and the cumulative recovery curve for this area continues to follow an upward trend that is currently approaching 70%. Reagent consumptions remain low as anticipated. In addition, a second delivery of gold in concentrate containing approximately 1,200 ounces was removed from the Company's processing plant prior to November month end.
Photo 1: Advancement of stacking and leaching activities at Santana heap leach pad
To view an enhanced version of Photo 1, please visit:
https://orders.newsfilecorp.com/files/4183/106895_e2d45d9e148f6918_002full.jpg
Mining and crushing activities at the project site continue to progress as operating experience is gained and the available Nicho Norte starter pit operating areas increase. As occurs normally during a start-up scenario it is expected that some variability in production metrics will continue for a period of time until the operations begin to stabilize. The Company continues to advance a number of project optimization efforts including:
-
Testwork to further quantify the relationship between overall gold recoveries and rock particle sizes;
-
Short term planning aimed at starting mining activities at the Nicho Main Zone to complement and expand the current mine production being sourced from the Nicho Norte starter pit;
-
Optimization of mineral crushing circuit parameters in order to maximize utilization of equipment currently available at site;
-
Continuing blast pattern modifications to minimize the amount of drilling/explosive required to obtain optimal rock fragmentation (minimize fragmentation levels in the unmineralized host rock in order to reduce overall blasting costs while maintaining high levels of fragmentation in the mineralized zones to reduce crushing requirements prior to gold leaching); and
-
Completion of new project laboratory facilities (all primary equipment is currently at site) to allow for significant reductions in both the costs and turnaround times for the analysis of production samples (rock and solutions) currently being sent off-site to third party facilities.
Photo 2: Nicho Norte Pit Development
To view an enhanced version of Photo 2, please visit:
https://orders.newsfilecorp.com/files/4183/106895_e2d45d9e148f6918_003full.jpg
Cautionary Statement
The Company made its production decision and has started the development and production of the Santana gold mine without having completed a feasibility study demonstrating economic and technical viability. As such, there may be increased uncertainty of achieving planned production levels, estimated recovery of gold, the costs associated with such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure. Failure to commence production would have a material adverse impact on the Company's ability to generate revenue and cash flow to fund operations.
Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press release under National Instrument 43-101.
For Further Information Please Contact:
Minera Alamos Inc.
Doug Ramshaw, President
Tel: 604-600-4423
Email: dramshaw@mineraalamos.com
Website: www.mineraalamos.com
Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: vvargas@mineraalamos.com
..............Bluetick