“ the Decision Bodies that the Project be allowed to proceed "... Dawson City Designated Office Evaluation Report
Quartz Exploration – Brewery Creek – 2021-0093
10.0 CONCLUSION OF THE ASSESSMENT
Under s. 56(1)(b) of the Yukon Environmental and Socio-economic Assessment Act, the Dawson City Designated Office recommends to the Decision Bodies that the Project be allowed to proceed, subject to specified terms and conditions. The Designated Office determined that the Project is likely to have significant adverse environmental and socio-economic effects in or outside Yukon that can be mitigated by those terms and conditions.
The terms and conditions of the recommendations are as follows:
1. Prior to conducting bulk sampling, a plan must be developed that describes how Metal Leaching and Acid Rock Drainage (ML/ARD) test work will be conducted and what mitigation and monitoring will be in place to reduce risks.
2. All bulk sample bags shall be removed from the site at the end of the exploration season, or by Dec 31st each year.
3. The Proponent shall follow a three-phased approach to mitigate effects to migrating caribou..." ETC!
https://yesabregistry.ca/api/uploads/a436c340-6d20-43cc-9722-b90e1ddfde65
This is great news! We all need some positive news in 2022!
The Yukon Environmental and Socio-economic Assessment Board could have easily just said NO so... Fortunately, they did NOT!