20 million for early works prgram "In parallel with its project financing initiatives, Trevali continues to advance certain aspects of RP2.0 in order to maintain the project schedule and mitigate the risks associated with the project as outlined in the Feasibility Study. The early works program, which has a capital budget of $20 million is expected to be financed from internal cash flows and consists of the following scope"
The CAPEX for RP2.0 is 111 million. I assume the 20 million of the paragragh above, are included in them. Is that so? Or are they in addition to the 111 million?