I am hoping for increased production moving forward.
I am hoping for increased production moving forward.This is from the Q3 MDA
With no restrictions in heap leach pad space, the crusher is expected to demonstrate further increases to throughput during the last quarter of 2021.
Management continues to focus on key crushing processes tied to conveyor moves, blockages tied to large rocks in the feed hopper, and ore loading restrictions to the crusher to maintain daily crushing rates above an average of 10,000 tons per day (current rate in the past three quarters was 7,500 tons).
https://elevationgold.com/investors/financial-statements/