RE:Excellent YT analysis on Trican Well Services!Thanks, great post. Due to the quality of the graphics and intimate knowledge of the company it almost comes on as an infomercial. But the average investor needs a presentation like this as they are clueless about the sector. One thing he missed is the built in demand for increased natural gas in BC when LNG Canada comes on stream in 2025. They'll start getting wells on line in 2024 because its going to take a lot of gas just to fill the 670 km of 48" line. Phase 1 of the LNG Canada plant will require 1.8 bcfper day. Phase 2 will require another 1.8 bcf. Phase 2 has not been approved for construction by LNG Canada. It would make the economics of the site as they will have all of the infrastructure and most of the permits in place. IE the site, pipeline from NE BC, wharf, power supply, etc. The 1.8 bcfpd capacity is about 1/3 of the entire amount of natgas BC presently produces.