RE:AFE confirms Gazania spud in SeptemberAs much as I hope you are correct, I will be very surprised if we do spud in the fall. The reason, Dana Petroleum currectly has the rig under contract and should have (assuming they did) spud back in April. They have THREE options. After Dana Petroleum is done, Petrofac will be drilling, they have TWO options. If no options are excersised, we should be spudding in September (ish). Each option taken probably pushes us back 4-6 weeks. If all five options by both companies are used, we could be pushed back 6 months. I wouldn't be surprised if we do not drill until March/April 2023. We could have 2 drills completed on the Canje block before we spud Gazania!