May 19, 2022: Field Activity Update - Week of May 16, 2022 May 19, 2022: Field Activity Update - Week of May 16, 2022
Drilling continued in the North Zone with two rigs, both deployed on the west slope.
Rig #1 located at the northern end of the old west slope road (now permitted), reached a depth of approximately 350m in hole N019 and will continue drilling operation.
Rig #2, deployed at the southern end of the west slope road, concluded N018 at a depth of approximately 625 meters. Downhole surveys on N018 are currently being conducted by the team. The rig is being partially disassembled for transport to the next drill pad to drill N020. An approved collar on old road south of N015 is the probable location of N020.
Across the river in Brasiles Rig #3 continued drilling B006 and currently stands at 420m. The team is already looking ahead to B007 and will begin road work and clearing of a pad over the next couple of days. Ahead of the rainy season the team has also been engaged in improving water run-off areas to direct water away from roadways and drill pads.
| |
Marking existing fractures before being transported to the core warehouse | Machine H-5 Santo Tomas Project (Gyro-Gamma Measurement) |
Machine H-7, Brasiles | Downloading Gyro measurement data (NO16) |
| |