Meanwhile ….. The Goose Mine is the Company’s first mine on the 80 km long Back River Gold District, a multi-generational mining district already with a high-grade world class gold endowment. Debt, streaming and equity financings were completed. Sabina had prepared tender documents and purchase orders which enabled the Company to quickly procure critical components necessary for this year’s sealift. Since last year, Sabina has procured, just over 70% of all direct purchases identified in the UFS. Earthworks at the plant site are ~67% complete, which reflects an overall Project civil works completion rate of ~40%.
and so it will progress. I'd love to take a site visit. In person, or virtually.