RE:RE:Q1 on sedarQ1 2022 in Campo Morado
Fortunately, production and recoveries in Campo Morado have been maintained, but it is worrying that after so long are not grinding 2500 tpd (Tonnes per day), continue with serious operating problems that should be foreseen that are causing substantial increases in costs and reduction in production. Increase capacity is perfectly viable, for example, in Q2-2018, immediately after declaring commercial production, came to grind 2200 tpd and in Q1-2020 from January 25 to February 22, after a long period without operating and before the closure forced by Covid, were achieved 2193 tpd for 11 continuous days. More worryingly, these deficiencies have increased the AISC from $55 in 2018 to $0.95 in 2021 and to $1.49 in Q1.