RE:RE:RE:RE:RE:RE:News out Wheeler wrote: Where in this NR do they suggest that they will finance only with equity? I'm not following your logic.
Highlights Average production, Year 2 to Year 16 of 173,317 tonnes of chemical grade 5.5% spodumene concentrate Average production, Year 2 to Year 16 of 51,369 tonnes of technical grade 6.0% spodumene concentrate Average production, Year 2 to Year 16 of 441 tonnes of tantalum concentrate Expected life of mine of 17 years Average operating costs of US$74.48 per tonne milled, US$540 per tonne of concentrate (all concentrate production combined) Estimated initial capital cost $US$357 million before working capital ** 100% equity basis for project **