NewsAfter 42 days of starting mining and milling operations in Tahuehueto are news, in the past 5 days process 195 tpd of ore and in 2 weeks more will conclude the crushing section and will be able to reach 500 tpd. Congratulations¡
It is understandable that at start-up stage the production is unstable, but the information should include key data such the quality of the ore, the metallurgical recoveries, the quality of the concentrates, are they as expected?
As indicated, the target in Q3 and Q4 is operate at 500 tpd, solve the problems with the equipment, complete the tailings storage facility and finish the construction of the plant to operate at 1000 tpd in Q1 2023.
Although too late and after a significant expense and loss of value, under this scenario ATLY becomes an attractive company to invest now.