RE:RE:RE:RE:RE:RE:RE:RE:RE:RE:RE:Check the LinkedIn page. Hi Kozmo,
1. The plant was moved to manono (this is TTXs site) and we are awaiting the mining Licence to move the equipment to the actual mining area. Note however that ground work and preperation at the mining site has begun
2. We have completed all applications and now awaiting the minister of mines to issue. Mining Licence.
3. the exploration on the alluvial was done already and diamond drilling was done to confirm the bedrock and as you mentioned continuity. So this was done. Reason why it wasn't published is because it was done by our team and is not the main exploration target. Email me and I can send you the project summary.
4. please look through what was published on this and we definitely plan to mine lithium, Tin and Tantalum. The additional 3500m on dumps K & G will be used to bring that into measured. Just those 2 dumps will be 14mio tons and we received further interesting results from the 10000m previously drilled. Please look at the last update on LinkedIn on this. It should be the last post from the team.
5. The plant was initially purchased by AfriMet and in 2021 it was agreed between Afrimet and TTX that the equipment will become assets of TTX. Hence the loan agreement that covers the Capex on the plant.
6. 3500m of additional drilling on dumps K & G, geochem and aeromagnetic surveys. Please also check the updates on LinkedIn on this.
I don't mind you asking questions like this. Many thanks