LAC Readiness for Lithium Production OperationsNow 1,650 employees onsite & ready to test the newly constructed Lithium processing circuits as key areas of the processing plant are preparing to commence operations shortly.
With 6 million total person hours without a loss time injury and the project budget in-line at $653 million spent to date, commissioning of the Lithium operations in Argentina is timely at near record high Lithium prices.
Lithium Americas looks poised for cash to begin flying-in the door.