QRR continuous, non-stop production starting in 3.5 months!  (December 2022)
 
  1. Complete system integration validation, about a quarter (1/4) of time is allocated to this phase, (June-August)
  2. Reactor startup, about one-twelfth (1/12) of time is allocated to this phase, (September)
  3. Four (4) process improvement tests, about one-sixth (1/6) of time is allocated to this phase, and (October-November)
  4. Operating the GEN3 QRR on a continuous, non-stop production basis during the remaining time. (December'22-May'23)