Update on drill progress @ HAMR's Phase II Program HAMR has completed the first of 11 drill holes for its Phase II diamond drill program at its past-producing Silver Strand Project in Idaho!
Using HAMR's established underground drilling station, Phase II is focused on expanding the known silver-gold mineralization while testing the potential for additional mineralized chutes.
The priority targets were previously generated based on a drone-supported magnetic survey, Phase I drilling results, and the integration of historic drilling data.
Approx. 1,100m of drilling is currently planned although HAMR has the ability to expand the program depending on core observations and assay results
HAMR is testing drill holes up to three times as deep as the previous phase of drilling with a series of other holes to test the system laterally to discover parallel chutes to the southeast of the main mine trend.
Phase II is expected to last approximately 7 weeks with assay results to follow in Q4 2022.
https://www.globenewswire.com/news-release/2022/08/15/2498107/0/en/Silver-Hammer-Reports-on-Drilling-Progress-at-the-Silver-Strand-Project-in-Idaho.html