RE:RE:MD&A / Financials out tonightl4, there is still a bit of confussion regarding the construction completion percentages, as it was noted in 2020 that the mine was 83% complete, and now it is reported that it is 50% complete.
That is a huge difference in completion rates so it would be nice to know where the 33% completion was lost. If it is repossessed equipment and machinery, so be it, as it is no secret, Wrx went through a rough financial stretch in 2020 / 21, but it happens and if the powers that be can get this novel mine up and running, thats the main goal.
I was under the impression though that the disposal well had already been completed, but it appears they are drilling another one so the question would be why?
Would be nice if shareholders are kept in the loop with progress updates, especially those like yourself who have been so patient for so long......................