RE:new pictures posted on Facebook pageThanks lexus4
Very interesting to see processing equipment being installed in the plant.
I wouldnt think a corporation would go to that expense unless they were fairly certain they had viable material requiring processing to run through the plant.
Would be very helpful if the corporation started regular updates regarding the completed stages of Phase 1, considering the massive 83% completion decline announcement to only 50% complete.
An update on the actual down hole mining tweaks would also be nice.
Have they now drilled extraction wells for each cavern?
Are the caverns being circulated once again?
The one hole injection / extraction method proved troubesome in Karnalytes tests due to heat irregularities within the well bore, and I wonder if Western encountered the same thermal issues with their original mine design.