RE:Production test volumesI didn't look in dept at the PEA but saw this and thought recent results were a little over this estimate. I could wrong.
A well network with two production well groupings consisting of 21 wells at each grouping, are located north and south of the CPF. One injection well grouping location consisting of 21 wells is located proximal to the CPF. The line of injection wells is located approximately 15 km and 16 km away from the line of production wells to the north and south, respectively. The selected well network, and its associated infrastructure, is designed to be capable of producing 140,000 m3 /day over a 20-year period with 92% availability, suitable for the production of 20,000 tonnes of lithium hydroxide monohydrate (LHM). The distance between each production well network and the injection well network was also designed such that the lithium void brine from the injection wells would reach the production wells after 20 years and achieve a maximum dilution of 5%