Savannah: Expected Progress for 2023 and onwardsExpected short term progress:
•Savannah to submit its revised EIA in 1Q 2023, deadline 17 March
•Regulator has 50 working days to review submission and issue its Declaration of Environmental Impact (DIA) decision – Decision expected in 2Q 2023
In long term:
2023 Resubmit EIA Q1, DIA decision Q2, licencing continued; Progress Definitive Feasibility Study (DFS), Decarb study & offtake discussions
2024 DFS & Decarb study completed; Env Licence received; offtake finalised
2025 Financing & Construction
2026 Complete construction, Commissioning & Production