RE:RE:Not sure if this matters ............Actually its commissioning and cooldown of loop 1 transfer piping and to reinstate boil off gas management system . Cooling the piping will probably take a week alone and more approvals will be needed as this process unfolds . Freeport has 3 liquifaction trains which have been idle for 7 months , everyone knows it will take time but at least the wheels are in motion . Freeport applied to begin restart procedures on Monday , PHMSA government inspectors were on site Wednesday and this approval was issued today , thats not bad . As I said , I'm not sure if it will matter tomorrow but it will as the plant begins operations again .