RE:First Two Mining Benches CompletedSo, the first two mining benches represent Pushback #1 which appears to have been completed.
These are at the crest of the current open pit where the pit wall is thinner, hence the much faster time to complete.
As they go deeper down the slope ( 45 deg ) of the current pit wall, the wall becomes thicker, hence the full year for each of pushback #2 ( 2023 ) and pushback #3 ( 2024 ).
So, we are on schedule with that planned activity.