New February 2023 Presentation up.
New February 2023 Presentation up. BRADSHAW SITE STARTUP PLAN AND OVERVIEW
• Complete ~25,000 m. diamond drilling program • Assemble the mining and technical team. This I believe will bring the resource over 2M oz Bringing the inferred below 800m to indicated allows for the 100k OPY production rate in 3year 3
• Complete the mine restart plan – 1.04 million tonnes of ore with average grade of 5.68g/t and 189K Oz gold (3-year mine plan).
• Average ASIC is US$1,400/oz within 3 years, and US$1,290 during the LOM.
• Complete surface vent raise development and surface infrastructure upgrade.
• Develop mine to sustain 400 tonnes-per-day (t/d) and ramp up to a minimum of 1,000 td.
• Current ~36 months ~1.04MT, target to mine 1300 t/d
Rather robust plan. compared to what were used to.