Mpama South Construction ProgressingThis was a over a month ago. So, things have progressed since.
Progress on the processing plant is as follows:
- EPCM, bulk earthworks, civils, and SMPPEI contracts have been awarded;
- Design and engineering is 75% complete;
- Procurement is 96% complete;
- Fabrication of structures and platework is 50% complete; and
- 11% of the processing plant has been moved to site.