RE:A few more pictures of the Steveville Plant
Not quite ready to transfer to the Steveville site. That was to happen in March with first helium by end of April. No way. There is more fabrication, adding little things like compressors and power system and valves and controls. Then some on-site testing. Before moving to Steveville, hooking it up, and then doing a lot of testing to produce high purity gas. (after initial testing to make sure it works). It is quite an adventure. The good thing (no the great thing) is that if it works as planned it will be amazing, and they will be set up to proceed with the next units like the Climax Shallow, Ogema, and Val Marie processors.
Then as they drill a deep horizontal to prove commerciality of Nazarre, they can start dreaming about the size of a facility they need to produce that and where they will get the $50 million plus for that.