TotalEnergies awards upstream FEED for Papua LNG The final investment decision for Papua LNG is scheduled for 17 months after the start of FEED, and first gas is planned for 44 months after project sanction.
Three FEED contracts were up for grabs for Papua LNG — the upstream central processing facility and well pads; the onshore and offshore pipelines; and the early works. Upstream had earlier reported Australia’s Worley as being in a good position to land the pipelines FEED.
TotalEnergies is operator of the upstream and pipeline components for Papua LNG while ExxonMobil will be responsible for construction and operation of the four electric liquefaction trains (e-trains) with a combined capacity of 4 million tonnes per annum as these will be sited within the US supermajor’s existing PNG LNG project.