$52M approved for DRPF equipment purchasesFrom the CC and PR;
Direct Reduction Pellet Feed Project ("DRPF Project") Update
- In connection with the recently announced positive findings of the DRPF Project feasibility study, the Board of Directors approved an increase of $52 million to the initial budget of $10 million announced on January 26, 2023, in order to maintain the DRPF Project's estimated 30-month construction period and a potential commissioning of the project in the second half of the calendar year 2025; and
- The DRPF Project remains on schedule with detailed engineering work advancing as planned.
During the Q&A it was confirmed that this will allow them to start ordering long lead time equipment required for them to meet their their target of commissioning in 2H 2025.