Good Gib-specific newsStuart McDonald, President and CEO of Taseko, commented “Mining operations are now well established in the lower benches of the Gibraltar pit, which have higher grades and larger, more consistent ore zones. Low mill availabilities had an impact on production in April and May, but in June and July we benefited from the softer ore in the Gibraltar pit and mill throughput averaged well above nameplate capacity. Copper production in June and July was 11 million pounds in each month. The Gibraltar pit will be the sole source of ore for the remainder of 2023. With increased copper production expected in the second half of the year we continue to track towards our original production guidance of 115 million pounds of copper (+/-5%).”