Jed Richardson on Kombat Underground Mine Progress
On track to establishment of the Kombat underground mine in early 2024, Trigon Metals (TM.v PNTZF) has provided an update on its progress with water levels decreasing and on track to be fully dewatered by year end.
This is significant as it will allow for mining to begin in the first half of 2024, only a short amount of time after TM achieving commercial production at the open mining pit.
Commenting, Jed Richardson, Trigon President and CEO, “Now that open pit mining has achieved commercial production, processing 1,000 tonnes per day of ore and shipping 250 tonnes of concentrate a week. It is important to understand work is well underway to expand the mill’s throughput and commence mining from the underground, leading to a tripling of production profile while lowering production costs and amplifying profitability.”